ISO 16484-1:2010Withdrawn

Building automation and control systems (BACS) — Part 1: Project specification and implementation

Systèmes de gestion technique du bâtiment (SGTB) — Partie 1: Spécification et mise en oeuvre d'un projet

This edition has been replaced by ISO 16484-1:2024.

Abstract / scope

ISO 16484-1:2010 specifies guiding principles for project design and implementation and for the integration of other systems into the building automation and control systems (BACS).

ISO 16484-1:2010 specifies the phases required for the BACS project, including:

  • design (determination of project requirements and production of design documents including technical specifications),
  • engineering (detailed function and hardware design),
  • installation (installing and commissioning of the BACS), and
  • completion (handover, acceptance and project finalization).

ISO 16484-1:2010 also specifies the requirements for as-built documentation and training.

ISO 16484-1:2010 is not applicable to operation and maintenance, nor is it applicable to retro or continuous commissioning, including a commissioning authority.

Life cycle

Replaced by

ISO 16484-1:2024PublishedBuilding automation and control systems (BACS) — Part 1: Project specification and implementationInternational Standard · Published 16 Jan 2024 · ISO/TC 205